|
|
|
    
Office
Construction
Project
The
Wisconsin
EMS
Association
Board of
Directors
and
staff
members
are
pleased
to
announce
the
construction
of a new
office
building
to house
the
entire
Wisconsin
EMS
Association
operations.
Watch
right
here as
we
chronicle
the
entire
process
from
finalizing
the
plans,
tearing
down the
existing
structure,
breaking
ground,
completing
the
shell,
designing
the
interior;
right up
through
move-in
early in
2009
|
Current
Activity
-
July 12,
2009 -
Following
the WEMSA
Board of
Directors
meeting,
the
building
project has
been
officially
deemed
completed.
Minor items
remain
along with
a "punch
list" of
items for
the builder
to address.
However,
the
construction
phase and
budget are
now closed.
Future
expenses
will be
posted to
the general
budget.
This will
be the
final entry
to the
current
activity
log.
-
July 1,
2009 -
Eleven
months
after the
first piece
of dirt was
moved, the
building is
essentially
completed.
Everything
on the
exterior is
done. A few
odds and
ends remain
inside, but
all are
very minor
in scope.
The WEMSA
staff has
been
working
from the
new
building
since early
May. The
project
will be
officially
termed
complete at
the July
12, 2009
Board of
Directors
meeting.
-
June 16,
2009 -
Security
camera
access has
been
configured
on-line so
staff can
monitor the
building
and review
camera
recordings
from any
Internet
connection.
The
electronic
keypad has
been
installed
on the
front door.
Various
shelves and
cabinets
have been
installed.
-
June 12,
2009 -
Landscape
lighting, a
brick wall
and
additional
plants and
shrubs have
been added
to the area
around the
sign.
-
June 5,
2009 -
The final
pieces of
networking,
audio and
video
distribution
and other
IT
equipment
have been
installed.
The
landscaping
around the
building
has been
completed.
-
May 29,
2009 -
Work has
been
underway
for over a
week to
complete
the
landscaping
on all
sides of
the
building.
-
May 16,
2009 -
The open
house is
held at the
new
facility.
About 75
people
attended
the event.
Photos of
the event
are
available
here.
-
May 15,
2009 -
A complete
and
thorough
cleaning is
underway in
preparation
of the
open house
taking
place in
less than
24-hours
-
May 12,
2009 -
The
monument
sign has
been set in
place and
the LED
message
board has
been
installed
-
May 11,
2009 -
The entire
parking lot
has been
paved.
After
nearly a
two week
delay, it
took less
than one
day to
complete.
-
May 4,
2009 -
Staff has
started
working out
of the
building
while the
final items
are
completed.
Unfortunately,
Time-Werner,
after
promising a
three day
turn-around,
is heading
into their
third week
working to
provide
Internet
service to
the
building.
-
May 1,
2009 -
The
building
inspector
has
provided
final
inspection
approval
for the
structure.
-
April 27,
2009 -
Cement
walkways
and a drive
to the
overhead
door has
been
poured.
Stone has
been
brought in
and grading
is taking
place to
prepare for
the parking
lot.
-
April 22,
2009 -
All of the
wall
connectors
for
telephone,
Internet,
audio,
video and
speakers
has been
installed
and tested.
-
April 19,
2009 -
Epoxy
flooring is
being
placed into
the media
studio.
-
April 17,
2009 -
A large
number of
final items
have been
worked on
during the
week
including
mounting
and
installing
the
conference
table,
large
screen TV,
media
center
cabinets,
front
reception
area
cabinets
and
counters,
book cases,
final
electrical
items and
final trim
items. A
cleaning
company
will be in
the
building
over the
weekend
starting to
remove all
of the dust
and debris
left over
from the
construction
process.
-
April 15,
2009 -
Final
plumbing
has been
completed
including
toilets,
sinks,
drains and
water
treatment
equipment.
-
April 13,
2009 -
All of the
remaining
hardwood
oak trim is
being
installed
throughout
the
building.
-
April 10,
2009 -
Kitchen
appliances
have been
installed
and
connected.
-
April 8,
2009 -
Sewer
connections
were made
through the
parking lot
and into
the
building.
-
April 6,
2009 -
Wood
flooring is
being laid
in the
remainder
of the
building.
-
March 29,
2009 -
Work has
started
laying out
the tile
for the
Walk of EMS
-
March 27,
2009 -
The
existing
well has
been
connected
to the
building.
-
March 25,
2009 -
All
interior
doors and
interior
window
frames have
been set in
place. Work
has started
installing
baseboard,
door and
window trim
has
-
March 24,
2009 -
The solid
glass wall
has been
installed
in the
conference
room.
Doors,
interior
windows and
trim has
arrived.
-
March 19,
2009 -
Work has
started
applying
ceramic
tile to the
bathroom
walls and
floor,
kitchen
floor, and
doorway
areas.
-
March 18,
2009 -
Cultured
stone has
been
applied
around the
fireplace.
-
March 17,
2009 -
Kitchen
cabinets
have been
installed.
Work is
being done
on
installing
electrical
outlets,
switches
and lights
along with
telephone,
data,
video,
audio jacks
and wall
plates.
-
March 13,
2009 -
The
painters
have
completed
their work.
Security
cameras
were
installed
both inside
and outside
and
connected
to the
digital
recorder.
-
March 10,
2009 -
With the
drywall
complete,
painters
began the
job of
painting
the entire
building,
using a
total of
five
different
colors.
-
March 9,
2009 -
Drywallers
started
spraying
the
knockdown
finish to
the
sheetrock.
-
March 2,
2009 -
With inside
temperatures
hovering
around 70
degrees,
mudding and
taping of
the drywall
has gotten
underway.
-
February 27,
2009 -
After a
week-long
delay, the
HVAC
company
installed
both
furnaces in
order to
provide
heat to the
entire
building to
allow for
mudding and
taping of
the
drywall.
-
February 20,
2009 -
WE Energies
connected
electricity
from the
utility
pole to the
building,
providing
electrical
power
throughout
the
structure.
The
drywallers
finished
hanging
sheetrock
throughout
the
building.
-
February 16,
2009 -
Today may
have been
the most
productive
since the
project
started.
Gutters
were hung
on the
entire
building.
Attic
insulation
was blown
in. WE
Energies
crews
completed
electrical
service on
the east
side of the
building
while
another
crew
completed
the gas
line on the
west. The
drywall
crew began
taping the
utility
rooms in
preparation
of furnace
installation.
-
February 13,
2009 -
Electric,
natural
gas, and
telephone
has been
trenched to
the outside
of the
building.
The gas and
electrical
meters have
been
installed.
-
February
12,
2009
-
Drywallers
have
finished
hanging all
of the
drywall and
installing
the rounded
corners.
They are
now waiting
for natural
gas to be
supplied to
the
building to
heat the
rooms for
mudding and
taping.
-
February 7,
2009 -
Work has
started on
hanging the
drywall.
Even though
it was a
Saturday,
workers
took
advantage
of 50
degree
temperatures
to work.
Most of the
offices and
portions of
the hallway
were hung
on the
first day.
-
February 5,
2009 -
Fascia has
been
installed
to the
exterior of
the
building.
All that
remains on
the outside
is
installation
of the
gutters
along with
trim work.
-
February 2,
2009 -
Insulation
is being
installed
into all of
the walls
and
ceiling.
The roof
will have
R-50 blown
in while
the outside
walls
receive
R-21. To
help with
sound R-11
has been
installed
in all of
the
interior
walls.
-
January 31,
2009 -
Wiring for
all of the
telephones,
computer
data,
speakers,
audio feed,
video feed
and
security
cameras has
been
completed.
All of the
outside
wall boxes
and seams
have
received
caulking.
-
January 26,
2009 -
The
fireplace
has been
installed
in the
center
conference
room.
-
January 20,
2009 -
All
electrical
wiring has
been
completed
and the
building
has passed
the
electrical
inspection,
clearing
the way for
insulation
followed by
drywall.
-
January 12,
2009 -
Additional
framing for
a wall with
a bookcase,
a secondary
utility
room inside
of the
media
studio/storage
area, and
the
conference
room
fireplace
has been
completed.
-
January 9,
2009 -
The front
entrance
unit has
been
installed
allowing
the
building to
be locked.
The HVAC
work has
been
completed.
The
building
will have
five
heating
zones
complete
with their
own
thermostat.
-
December 22,
2008 -
The
electricians
have
started to
wire the
building
both inside
and outside
for all
electrical
connections.
Three
electrical
services
are
planned:
one for
common
areas and
exterior
lighting,
one for the
majority of
the
building,
and one for
the media
studio and
potential
future
expansion.
-
December 21,
2008 -
Rough
plumbing,
the shower
stall,
natural gas
lines and
water lines
have all
been
installed.
-
November 25,
2008 -
The masons
have
finished
with the
outside
brick work.
Once the
front
entrance
unit is
installed
the
building
will be
secured.
Much of the
HVAC duct
work has
been
installed.
-
November 21,
2008 -
Due to
several
reasons,
the
portions of
the
building
originally
specified
for hardy
plank
siding will
now be
brick. That
means the
entire
exterior
will be
dressed in
decorative
block and
brick with
no portions
done in
wood
siding.
-
November 10,
2008 -
The masons
are making
significant
progress on
the outside
brick work.
Most of the
building is
full brick
with only
the rear
portion
using hardy
plank
siding.
-
November 7,
2008 -
Duct work
has started
for the
HVAC.
-
November 6,
2008 -
Windows
have been
placed in
most of the
window
locations.
One window
and one
door have
been
back-ordered.
-
November 1,
2008 -
The
electrician
has set the
electrical
service
panels in
preparation
for
connecting
power to
the
building.
-
October 29,
2008 -
Masons have
started
work on the
outside
brick and
block.
-
October 29,
2008 -
All of the
roof work
including
shingles
and vents
has been
completed.
Windows are
scheduled
to be set
during the
first week
of November
followed by
brick work.
-
October 21,
2008 -
With the
roof now
ready for
shingles,
roofers
have
arrived to
complete
that job.
At the same
time, free
fill is
being
delivered
from
several
sources.
The grade
needs to be
elevated by
about one
foot.
-
October 11, 2008 -
With roof
trusses now
in place,
most of the
overhangs
have been
built. Much
of the roof
sheathing
has also
been
installed.
Preliminary
HVAC, and
electrical
will start
shortly as
will window
placement
and
skylight
placement
followed by
the outside
brick work.
-
October 1, 2008 -
Work has
started to
set the
roof
trusses in
place. The
rather
complex
roof will
take about
a week to
complete.
-
September
26, 2008 -
Framing for
the
conference
room has
been set in
place.
-
September
25, 2008 -
Framing for
the inside
offices has
been
completed.
-
September
24, 2008 -
Outside
sheathing
and foam
board has
been placed
around the
structure.
-
September
23, 2008 -
The
concrete
floor has
been
poured.
-
September
16, 2008 -
A maze of
3" PVC
piping has
been laid
into the
floor. This
will allow
for data,
audio,
video,
cable TV,
phone, and
other wires
to be
pushed
underneath
the floor
into the
various
offices.
-
September
9, 2008 -
Framing for
all of the
outside
walls has
been
completed.
Roof trusts
have been
ordered.
The steel
beam for
the front
entrance
has been
placed.
-
August 29,
2008 -
Lumber has
been
ordered and
has started
to arrive.
Following
the Labor
Day
weekend,
labor is
scheduled
to start
with the
framing of
exterior
walls. This
will be
some of the
most
tangible
evidence of
progress.
-
August 28,
2008 -
Sewer,
drain and
water lines
have been
set in
place
within and
below the
current
stone
flooring
base.
Having all
of these
items in
place
clears the
way for the
internal
floor to be
poured when
all of the
other items
are ready.
-
August 27,
2008 -
Water and
electrical
lines have
been ran
below the
ground to
the
existing
well on the
far
northwestern
corner of
the lot.
They now
enter the
structure
on the wall
closest to
the well
and then to
the utility
room within
the cement
floor.
-
August 22,
2008 -
Backfilling
has been
completed
around the
entire
structure.
Next up the
crew will
start
framing the
outside
walls. At
the same
time,
engineering
for the
trusts will
be
completed
and trust
construction
will begin
at the
lumber
yard.
-
August 14,
2008 -
The
concrete
footings
have cured
for a full
week. The
forms for
the poured
walls are
in place
and the
walls have
been
poured.
Another
seven days
will be
needed
before
backfilling
takes
place.
-
August 5,
2008 -
With the
necessary
documents
in hand,
the initial
excavation
has been
completed
and the
footings
poured.
Block and
preliminary
utility
connections
are the
next items
on the
schedule.
-
July 21,
2008 -
State,
county and
local
approvals
have all
been
obtained
along with
the
necessary
building
permits.
While
original
bids from
the various
sub
contractors
are now
firmed up,
the project
is still
moving
forward
starting
with
excavation
for the
foundation.
-
July 1,
2008 -
The
Wisconsin
EMS
Association
has started
to work on
obtaining
donations
from anyone
who is
willing to
provide
goods or
services in
the spirit
of
supporting
our
non-profit
organization.
Michael
Hood,
Director of
Sales and
Customer
Service, is
the person
to contact
if you
might be
able to
help.
Examples of
just a few
of the
items we
are
currently
hoping to
find donors
for include
a 12'
garage door
with
opener;
dumpster
service;
on-site
toilet
services;
Silt fence
with
installation;
Site survey
for staking
the
building
footprint;
Phone,
data, and
video
network
installation.
If you or
someone you
know can
help to
make the
WEMSA
offices a
reality,
please
contact
Michael
Hood
directly at
414-755-2774
or
mikeh@wisconsinems.com.
Recognition
that could
also
include
magazine
advertising
and
conference
sponsorships
may also be
available
to those
who donate.
|
|
|
|
|
 |
 |
 |
FOLLOW ALONG FROM CONCEPT TO
COMPLETION
With a final price tag expected
to top three quarters of a
million dollars, the Wisconsin
EMS Association office project
is the largest and most
expensive that the organization
has ever embarked on. Once
completed it will provide the
necessary infrastructure to
catapult the Wisconsin EMS
Association through the next 10
to 20 years of progress. Large
enough to house over one dozen
full-time workers and spacious
enough to host meetings with 25
or more participants, the
Wisconsin EMS Association
offices will serve to play a
significant role in the
organization's success.
|
 |
|
|
|
|