Wisconsin EMS Association Office Photos
 

Building Information

Office Home

Final Plans

Original Plans

Photos

Location Map

 
Page Last Updated 
November 18, 2008
 
© 2008 Wisconsin EMS Association
Contact Us
1-800-793-6820
 

  Photos from the construction site
 
Click on any photo to see a larger version

November 18, 2008 - The masons have just about completed the brick work

November 18, 2008 - All that remains for the masons is to complete the front door and window brick

November 17, 2008 - Duct work is being installed for the heating and air conditioning system

November 17, 2008 - Duct work is being installed for the heating and air conditioning system

November 12, 2008 - Substantial progress has been made on the outside brick.

November 12, 2008 - Most of the windows have been installed

November 12, 2008 - A close up view of the coined corners and outlined window

October 31, 2008 - Brick work is underway starting with the decorative block

October 31, 2008 - Brick work is underway starting with the decorative block

October 29, 2008 - The roof has been completed

October 29, 2008 - The roof has been completed

October 29, 2008 - The roof has been completed. Looking from the west

October 29, 2008 - Fill has been delivered to finish the back filling to grade

October 29, 2008 - The roof has been completed. Looking towards the front of the building

October 23, 2008 - The roofers have started to lay the shingles

October 23, 2008 - The roofers have started to lay the shingles. Looking from the southwest corner

October 23, 2008 - Shingle bundles ready to be laid.

October 23, 2008 - Workers elevate the shingles to the roof

October 20, 2008 - Fill has started to arrive from several free sources to even out the landscape

October 11, 2008 - Much of the roof is now complete. Shingles should be installed within the next 10 days.

October 11, 2008 - Much of the roof is now complete. Looking from the Southwest corner.

October 11, 2008 - The Southeast roof area of the buliding is still under construction

October 11, 2008 - Looking at the current progress to the front of the building.

October 8, 2008 - Work continues on the roof and overhangs

October 8, 2008 - Work continues on the roof and overhangs

October 8, 2008 - Work continues on the roof and overhangs

October 8, 2008 - Work continues on the roof and overhangs

October 6, 2008 - The view from inside. The large header is for the glass conference room wall

October 6, 2008 - Looking in from the front entrance

October 2, 2008 - Work starts on the roof

October 2, 2008 - Work starts on the roof

October 2, 2008 - Work starts on the roof. Looking toward the rear of the building

September 25, 2008 - Framing for interior walls is underway

September 25, 2008 - Framing for interior walls is underway. Looking in from the front door

September 25, 2008 - Framing for interior walls is underway. Looking east from the west offices

September 25, 2008 - Framing for interior walls is underway

September 24, 2008 - Outside panels and foam board has been placed.

September 24, 2008 - Outside panels and foam board has been placed.

September 23, 2008 - Cement floor has been poured

September 23, 2008 - Cement floor has been poured. Looking from the northwest towards the front doors

September 23, 2008 - Cement floor has been poured. On the back wall of the media studio looking into the main building

September 16, 2008 - Ready for concrete flooring to be poured. The hallway and conference room are market by the rebar

September 16, 2008 - Ready for concrete flooring to be poured. The hallway and conference room are market by the rebar

September 16, 2008 - Three inch PVC pipe is laid throughout the floor to allow for future wiring needs. The conference room is in the foreground.

September 16, 2008 - Bathrooms and utility closet

September 9, 2008 - Outside framing complete. Looking at the entrance, south and east walls

September 9, 2008 - Outside framing complete. Looking at the back and west side of the building

September 9, 2008 - Outside framing complete. Looking east at the west end wall

September 9, 2008 - Looking at the media studio and storage area on the right. Kitchen area and bathrooms are along the wall to the left

September 9, 2008 - Inside of the structure looking at the north and east walls. The media studio is in the back.

September 9, 2008 - Inside of the structure looking at the west and north walls. Each window or knock-out represents an office area

September 5, 2008 - Construction area from the air

September 5, 2008 - Construction area from the air

September 5, 2008 - Construction area from the air

August - 22 Backfilling completed and ready for framing and cement flooring

August - 22 Backfilling completed and ready for framing and cement flooring

August - 22 Backfilling and stone base completed with storage garadge in foreground

August - 22 Backfilling completed looking from the front enterence

August 14, 2008 - Poured walls with the forms still in place - Taken from the Northwest

August 14, 2008 - Poured walls with the forms still in place - Looking from the Northwest

August 14, 2008 - Poured walls with the storage are to the far left

August 14, 2008 - Poured walls with the forms still in place - From the Northwest corner of the building

August 14, 2008 - Inside of the poured walls looking to the west

August 7, 2008 - Cement trucks standing by and ready to pour

August 7, 2008 - Footings being filled

August 7, 2008 - Using this boom they are able to lay cement to all of the footings

August 7, 2008 - Looking towards the southeast at the rear of the building

August 5, 2008 - Ready for cement footings to be poured. The storage garage is on the left side

August 5, 2008 - Footings looking from the southwest corner

August 5, 2008 - Footings for the main portion of the building looking from the north to the south

August 5, 2008 - Down in the trenches

July 30, 2008 - Looking from the west at the now vacant lot ready for construction

July 30, 2008 - This second drive into the lot from Racine Avenue will be removed

July 30, 2008 - The basement has been compress-filled to prevent settling

July 30, 2008 - 1.3 acres of wide open space ready for construction of the 4,200 sq ft building

June 19, 2008 - The building came down in less than 45 minutes

June 19, 2008 - Several dumpsters were used to haul away the remains

June 19, 2008 - All that stood was the old bank vault made of 1' thick cement on all sides, floor and roof

June 19, 2008 - A wrecking ball had to be brought in

April 9, 2008 - The origional building and lot from Hwy 36

April 9, 2008 - The original building

April 9, 2008 - The original building looking from the east

April 9, 2008 - WEMSA Office location with ACE Hardware next door